Progress reported as multi-phase roadworks continue
Work on the Spalding to Pinchbeck active travel improvements has advanced through July and will carry on through the summer and autumn, Lincolnshire County Council has confirmed. The scheme is being delivered in several discrete phases along the route between West Elloe Avenue and Woolram Wygate, with a mixture of footway construction, drainage, traffic signal installation and utility work under way.
According to the council's update, crews completed the National Grid works for the first phase and have finished around 65% of the west-side footway for Phase 1. Preparation for Phase 2 has included trial holes to check the depth of existing apparatus, breaking out old kerbs and footways and installing new traffic signal equipment.
What residents can expect in August and beyond
Planned activity for August includes finishing the west-side footway in Phase 1, clearing vegetation to allow lighting column installation in Phase 2, completing footway and drainage works for Phase 2 and putting in the new traffic signal installation for that section.
- Phase 1 – West Elloe Avenue to King’s Road (mid‑June to mid‑October): one-way northbound with National Grid works taking place within a lane closure.
- Phase 2 – West Elloe Avenue to Park Road (late July to early September): multi-way temporary traffic signals; Park Road closed 24/7 near the level crossing.
- Phase 3 – Park Road to Woolram Wygate (early September to late October): one-way northbound on Pinchbeck Road north of Park Road; Woolram Wygate closed 24/7.
- Phase 4 – Hospital Road to Woolram Wygate (early September to mid‑December): one-way northbound on Pinchbeck Road; access to the hospital from the north will be maintained.
The council has published diversion routes for each closure and warns that further phases will bring additional temporary traffic arrangements. Some works will require permanent closures where they abut rail level crossings; these closures are in place for safety given proximity to the tracks.
Practical information for road users
Drivers and pedestrians should be prepared for local diversions and delays. Notable diversion routes outlined by the council include West Elloe Avenue, Holbeach Road and the A16 for Phase 1 traffic changes. For phases affecting Park Road and Woolram Wygate the council lists local alternative streets such as Pinchbeck Road, Kings Road and Bond Street Court.
| Phase | Location | Timing |
|---|---|---|
| Phase 1 | West Elloe Ave to King’s Road | mid‑June to mid‑October |
| Phase 2 | West Elloe Ave to Park Road | late July to early September |
| Phase 3 | Park Road to Woolram Wygate | early September to late October |
| Phase 4 | Hospital Road to Woolram Wygate | early September to mid‑December |
Residents who rely on the route for daily travel, hospital appointments or deliveries are advised to check the council's updates for exact dates and specific diversion maps. Some utility companies, including Cadent Gas and the National Grid, are working within the scheme, which can affect the phasing and timing of local closures.
The council's staged approach aims to deliver improved walking and cycling links while maintaining access where possible, but it will require patience from road users while the works continue through the late summer and into the winter.